Wednesday, December 25, 2013

Tuesday, December 24, 2013

The last week has seen a lot of activity at the house. Once the concrete had set, the framers were up and running.

The framer for the job is Jeff Cunningham of Cunningham Development. Phone number 970.471.3615. 

Monday, December 16, 2013

Friday, December 13, 2013

Men at Work


  
 Pouring Concrete - This looks like hard work!



  Later that morning...
     
  Yeah!

Wednesday, December 11, 2013

View from the New House

 


    The dirt is ready.
  The land is level. The Rebar is in place. The sand is on.
  Now we just need some concrete. 



The elevator box is 
ready to be cast. 


Monday, December 2, 2013

The Foundation


   Getting ready to pour concrete.



   The new house has a curved front like the old one did.



   







Rebar is in. The trenches are dug. Duffy crew is getting 
the foundation prepared for the concrete.